The 737-page Environmental Impact Assessment (EIA), prepared by Samaras & Partners on behalf of PPC, sets out the detailed design of the first phase of the investment, which forms part of the energy group’s strategic plan for 2030.
According to PPC’s stock exchange announcement dated 23 April 2026, the development of the data centre is part of a broader investment programme worth €24 billion, aimed, among other objectives, at almost doubling the group’s installed capacity to 24.3 GW by the end of the decade.
PPC has earmarked €1.2 billion in capital expenditure for the first phase of the data centre, with operations targeted to commence by the end of 2028.
The Development Model and the Agreement with Amazon
On 17 September 2026, PPC announced that it had signed a binding Memorandum of Understanding (MoU) with Amazon Web Services, setting out the key commercial terms governing the development of the project. The business model separates investment in the property and energy infrastructure from investment in the technological equipment.
PPC will provide the land, develop the buildings and supporting energy infrastructure, and meet 100% of the data centre’s electricity requirements through renewable energy supplied under long-term Power Purchase Agreements (PPAs).
AWS, for its part, is expected to lease the facilities for an initial period of 15 years following completion of construction, assuming responsibility for the installation and operation of the IT equipment.
This investment model will generate two distinct revenue streams for PPC: rental income from the property and supporting infrastructure, and revenue from electricity supply.
According to an information note issued by the Office of Economic and Commercial Affairs in New York on 5 October 2026, the total budget for the first phase, including technological equipment, is estimated at €3.5 billion.
At the same time, the two companies intend to explore the possibility of a broader, multi-year partnership in cloud computing and artificial intelligence, with the aim of also supporting PPC’s own digital transformation.
Four Buildings Across a 450-Stremma Site
The project will occupy an area of approximately 450 stremmata (450,000 sq. m.) at the site of the former Agios Dimitrios lignite-fired power station. According to the EIA, the station’s five generating units were permanently decommissioned on 15 June 2026, bringing decades of lignite-based activity in the area to an end.
The development plan provides for the construction of four identical buildings, each accommodating five data halls, with a capacity of 12 MW per hall. The total installed capacity of the IT equipment will amount to 240 MW, while the complex’s maximum power demand, including cooling systems and auxiliary facilities, will reach 300 MW.
The total gross floor area of the facilities will amount to 77,360 sq. m., while the overall site coverage will reach 111,640 sq. m. Of this area, 71,560 sq. m. will comprise buildings, while the remaining 40,080 sq. m. will accommodate outdoor electromechanical equipment.
The project is a hybrid co-location data centre designed to support both conventional cloud computing services and computationally intensive artificial intelligence applications.
The complex will feature independent power supply, cooling, telecommunications connectivity, fire protection and physical security systems, as well as administrative and auxiliary facilities.
Annual Energy Consumption of 2.33 TWh
The availability of existing energy networks, industrial land and infrastructure represents a key advantage of the selected location.
The annual electricity consumption of the facility at full load is estimated by the consultants at 2.33 TWh. Approximately 90.3% of the energy will be consumed by IT equipment, with the remaining 9.7% allocated to cooling systems and auxiliary facilities.
Based on the design assumptions, the complex’s Power Usage Effectiveness (PUE) is estimated at 1.1071.
Particular emphasis is placed on the use of closed-loop cooling systems and direct liquid cooling of IT equipment, a technology associated with the increased cooling requirements of artificial intelligence applications.
PPC maintains that the facility’s water requirements will amount to just 0.6% of the volume previously required by the lignite-fired operations at Agios Dimitrios. The possibility of recovering and utilising waste heat generated by the data centre is also being examined.
The New Regulatory Framework
In its presentation of nine-month 2026 financial results to investors, PPC places particular emphasis on the new regulatory framework governing large-scale data centres, which was approved by Parliament on 11 November.
Among the provisions highlighted by the company are priority access to grid connections for projects with a capacity exceeding 200 MW, a requirement for at least 60% of annual electricity consumption to be covered by new renewable energy installations, and the submission of a grid connection guarantee of €200,000 per MW.
The framework also provides for investors to bear the cost of grid connections and network upgrades, as well as to pay an annual compensatory fee to the local community.
PPC’s management estimates that the new framework will favour projects with a high degree of maturity and secured access to renewable energy, such as the Kozani development.
The Prospect of Expansion to 1 GW
The initial 300 MW phase forms part of a broader development plan that envisages the possibility of expanding the complex’s capacity to up to 1 GW.
In its nine-month financial results announcement, PPC clarifies that any expansion will be subject to mutual agreement with AWS, prevailing market conditions and the signing of additional definitive agreements.
Published estimates put the value of PPC’s wider investment plan at €5.75 billion in the event of full development. This figure does not relate exclusively to the data centre’s buildings and facilities.
A Construction Site Employing 2,500 Workers
Construction of the first phase is expected to take 24 months and will include earthworks, foundation works, construction of the building structures, electrical grid connection works and installation of electromechanical equipment.
According to the EIA, an average of 1,500 workers are expected to be employed during the construction period, with the workforce rising to 2,500 during peak construction activity.
The influx of workers and specialised construction crews is expected to generate additional demand for housing, accommodation, commercial premises and services across the wider Kozani area.
However, as PPC points out, several key steps remain outstanding, including the finalisation of agreements with AWS, completion of the due diligence process, securing the required electricity grid connection and obtaining the necessary regulatory approvals.