This shall be the output of the ten-year development program of the Transmission System for the period 2023 - 2032 that was put into consultation by RAE (it had already been put into consultation by IPTO at the beginning of the year) as well as the corresponding program for the period 2022-2031 that was approved by Principle.
In particular and according to the data unveiled.
The fourth phase of the interconnection of the Cyclades will save 1.5-3 billion euros in the period 2025-2049. The project includes the interconnection with Serifos via Lavrio and the interconnections Serifos - Milos, Milos - Folegandros, Folegandros - Thira and Thira - Naxos as well as the interconnections of the islands of the Southwest Cyclades (Kythnos, Sifnos, Anafi, Amorgos, Donoussa and Astypalaia). . According to ADMIE's estimate, the project will be completed in 2024.
-A benefit of 2.7-3.6 billion Euros is expected from the interconnection of the Dodecanese for the period 2029-2053. The project is expected to be completed in 2028.
-And from the islands of the North-East Aegean (includes the connections with Lemnos via the KYT N. Santas and Skyros via the KY Aliveri, the connections Limnos - Lesvos, Lesvos - Chios, Chios - Samos, Samos - Kos and Lesvos - Skyros as well as and Ikaria and Agathonisi) a benefit of 1.6-1.9 billion is expected for the period 2030-2054. The completion horizon is 2029.
With regards to the second phase of the interconnection of Crete (Heraklion - Attica), the completion horizon of the project remains pending due to delays in licensing, effects of the pandemic, etc. RAE, with the decision to approve the 2022-2031 program, sets a deadline of the second semester of 2023 while ADMIE in the new 2023-2032 decade states that the project will be completed in 2024.