The project involves the construction of a stormwater pipeline network in the Agia Filothei area, which is funded by the Attica Region. The following works are planned:
- Pipeline on Antheon Street, from Neapolis Street to Eleftherias Street.
- Pipeline on Nikis Street, from Tembon Street to the junction of Ziria & Pangaio Streets.
- Pipeline on Tembon, Gkionas, and Pangaio Streets, from Nikis Street to Mainalou Street.
- Pipeline on Eleftherias and Ag. Oros Streets, from downstream of the intersection of Eleftherias and Nikis Streets to Patmou Street.
- Pipeline on Neapolis and Antheon Streets, from Gorgopotamou Street to Fleming Street.
- Pipelines on Neapolis Street (left and right of the median) from Gorgopotamou Street to approximately 50 meters towards the intersection of Neapolis and Pentelikou Streets.
Additionally, the reconstruction of sections of the existing network is planned, specifically on sections of Hippocratus, Agrafon, and Apostolou Pavlou Streets.