Today's decision of the Kalavrita Court of First Instance, forces the
Western Corridor of the Indipendent Power Transmission Operator (IPTO)
in the Peloponnese, to stop its works, due to the temporary order
secured by the nuns of a local monastery, until the final court
decision.
It is reminded that the precautionary measures were submitted by the
Monastery of Agioi Theodoroi on November 27, 2020, to prevent the
placement of two pillars (at a distance of half a kilometer from the
monastery), which would complete the energy upgrade of the Peloponnese
to the High Voltage (400 kV). The € 110m project is now necessarily on
hold and is expected to remain in this state for one more month, the
period estimated to be needed until the final court decision.
In fact, the project is already 98% ready and when it operates, it will
enable, among other things, the natural gas unit of PPC "Megalopolis 5"
to operate at its maximum power capacity, along with new RES that will
be installed in Peloponnese.
Extension to the "block" of the IPTO Western Corridor
Extension to the "block" of the IPTO Western Corridor
Extension to the "block" of the Western Corridor as a result of the appeal of the Agioi Theodoroi Monastery was decided by the court.
Share
Copy Link
RE+D magazine
21.01.2021