The "Die Welle" project, located near Regensburg, has been generating electricity since August 2024.
The manufacturer offers a 12-year warranty on the product, with a 30-year warranty on the performance of the units. Additionally, the inverters are covered by a five-year warranty.
The solar farm in Barbing has been supplying energy to the grid since August 2024. The installation includes 17,600 solar modules and 28 inverters, covering an area of 110,000 m². The site is secured with long-term lease agreements lasting 20 years, with two options for five-year extensions. The system has a total capacity of 10 MWp.
For "Die Welle" and other comparable high-yield renewable energy park investments, EURAMCO forecasts total payouts of approximately 170%, with moderate growth expected at 165% and a positive deviation of at least 175%.