Aktor delivers the section of the SEBES - TURDA highway
Aktor delivers the section of the SEBES - TURDA highway
  Investments  |  Listed  |  Infrastructure  |  Balkans

Aktor delivers the section of the SEBES - TURDA highway

Share Copy Link
RE+D magazine
09.12.2021

One of the largest and most updated road projects in Romania, section 2 (Lot2) of the Sebes - Turda highway, was delivered at the end of November by AKTOR, a company of the ELLAKTOR Group, to the competent authorities of Romania.

The latest section of the 70-km Sebes-Turda motorway (A10) in western Romania was delivered on November 30, according to local news agency Economica.net.

The section allows direct access from Cluj-Napoca to the main east-west route in Romania: Constanta-Bucharest-Pitesti-Sibiu- Arad-Nadlac.

The contract for section (Section 2) - was signed in November 2014, with the consortium formed by Aktor and Euroconstruct Trading initially having the deadline for completion in October 2016.

At the time of signing, the value of the contract was €120million, excluding VAT. For a 1.5km parcel of the 24km Section 2, the traffic will be restricted to one lane until April-May 2022.

The speed limit for the 1.5km segment is restricted to 60 km/h, while for the entire 24-km section commissioned on November 30, the speed limit is restricted to 100 km/h.