Construction of the scheme has commenced with cores for each block now complete and completion still on track for 2026.
Excavations have been completed over 75% of the total volume of 400,000 m3 of soil and concreting of walls over 45%.
The project will add 35 rooms to the hotel, 11 more than the original feasibility study allowed, bringing the number of rooms to 184.