The development of the freight center in the Thriasio field is becoming more vague, after the "ultimatum" of the EU Competition Commission (DG Comp) which requests, for the implementation of the project, on the one hand the doubling of the entrance fee by the concessionaire at the same time with the reduction of the concession period to 37 years, while stipulating that “if the return on investment exceeds 9% this will be shared between the parties ", without however specifying whether this concerns the excessive percentage or determining how it will be shared.
The acquisitions of the two properties were financed through funds raised by the Share Capital Increase completed in August 2019
Logistics in Thessaloniki are gaining momentum as the works for the upgrade of the facilities in the port and in the railway network progress.